EPC + O&M · Penang, Malaysia
Plywood mill power and steam
- 1.5 MW
- Power
- 12,000 MWh/yr
- Annual output
- Plywood offcuts
- Fuel
- Plywood manufacturer
- Customer
- COD 2026
- Commissioning
01
02
03
04
05
Project overview
1.5 MW of onsite power from plywood offcuts.
A CNP-delivered onsite plant supplying electricity and contracted process steam from mill residues and local plantation wood, under a long-term energy agreement.
- The challenge
- A 24/7 plywood operation paying rising grid tariffs and firing coal for process steam, with a steady stream of wood residue on site.
- What CNP delivers
- A CNP-delivered onsite plant supplying electricity and contracted process steam from mill residues and local plantation wood, under a long-term energy agreement.

On site
Project photos.
01 / 04Impact
- 12,000 MWh
- Renewable electricity a year
- 8,400 tCO₂
- Emissions avoided a year
- 2,500 t
- Biochar produced a year
- 6,000 tCO₂e
- Carbon removal a year
Plant configuration
The plant.
- CNP role
- EPC + O&M
- Capacity
- 1.5 MW
- Heat
- 5 t/h process steam
- Fuel
- Plywood offcuts
- Fuel use
- 12,500 t/yr
- Operating hours
- 8,000 h/yr
- Availability
- 95%
- Location
- Penang, Malaysia
- Commissioning
- 2026
Scope
What CNP delivered.
- Project development
- Engineering and design
- Plant supply and fabrication
- Installation and commissioning
- Operations and maintenance
- Biochar and carbon removal
Asia Green Wood
Customer
Plywood manufacturer
“Turning our own residue into power and steam gives us energy costs we can plan around, and takes coal out of our process.”