Carbon Negative Power

Insights/Industrial Energy

Behind-the-Meter Power: A Buyer's Guide for Industrial Sites

Generating power on your own side of the meter changes what you pay, how reliable your supply is and how exposed you are to tariff changes. A practical guide to evaluating it for an industrial site.

25 August 20264 min readCarbon Negative Power

Behind-the-Meter Power: A Buyer's Guide for Industrial Sites

Key takeaways

  • Behind-the-meter power avoids network charges and tariff escalation on the energy it replaces.
  • The best candidates run long hours, have steady load and face rising or unreliable grid supply.
  • Heat demand improves the economics substantially, because a local plant can supply it and the grid cannot.
  • Energy-as-a-Service structures remove the capital requirement from the customer.

Industrial energy buyers used to have two choices: take the grid tariff, or build and run their own power station. Behind-the-meter generation delivered as a service sits between the two, and for many sites it is now the lower-cost and lower-risk option.

What behind-the-meter means for your bill

A grid tariff bundles several things: the energy itself, transmission and distribution network charges, capacity or demand charges, policy levies and the retailer's margin. Power generated behind the meter replaces the kilowatt-hours it supplies, so it avoids most of those components on that share of your consumption.

It also changes your exposure. Grid tariffs move with fuel prices, network investment programmes and regulatory resets. Malaysia's July 2025 tariff reset is a recent example — see our analysis. Power from an onsite plant is priced under a long-term agreement, with escalation set in the contract rather than by the network.

Which sites suit behind-the-meter generation

The strongest candidates share most of these characteristics:

  • Long operating hours. Two- or three-shift or continuous operation, so the plant runs at high utilisation.
  • Steady base load. A floor of demand that is always there, typically from 1 MW upwards.
  • Heat demand. Steam, hot water or process heat for dryers, kilns, boilers or presses.
  • Local fuel. Agricultural or wood residues on site or nearby.
  • Grid pain. High or rising tariffs, frequent outages, voltage problems, or no capacity for expansion.
  • Space. Room for a plant footprint and fuel storage near the load.

A site with three or more of these is worth assessing.

Heat changes the economics

A power plant converts only part of its fuel energy into electricity. The rest becomes heat. A plant at a remote power station rejects that heat to the atmosphere; a plant at your site can deliver it to your process.

For sites with steam or process heat demand — mills, dryers, kilns, food processing — recovered heat can displace boiler fuel such as diesel, LPG, heavy fuel oil or coal. That second revenue stream from the same fuel often makes the difference between a marginal project and a strong one.

Behind-the-meter versus an off-site renewable PPA

Many companies already buy renewable electricity through an off-site PPA — a contract with a solar or wind farm elsewhere on the grid. The two approaches solve different problems:

Off-site renewable PPA Behind-the-meter onsite plant
Where the power is made Elsewhere on the grid At your site
Network charges Still paid on all consumption Avoided on the share supplied onsite
Reliability of your supply Unchanged — still the grid Improved; can run through grid outages
Firmness Usually intermittent (solar, wind) Continuous, 24/7
Heat Not supplied Recovered heat available
Grid capacity needed Unchanged Reduced; can enable expansion without upgrades

An off-site PPA mainly changes the carbon attribute of your electricity. A behind-the-meter plant changes its cost, its reliability and where it comes from.

Common concerns, answered

"We don't want to run a power station." Under Energy-as-a-Service you don't: the supplier operates and maintains the plant.

"What if the plant fails?" The grid connection remains as backup, and the agreement sets availability commitments with remedies.

"What if our production changes?" Agreements can include flexibility in minimum volumes, and modular plants can be resized.

"Will it disrupt the site during construction?" Most of the plant is built off site; the tie-in to your electrical system is planned for a scheduled shutdown.

The questions to ask a supplier

  1. What is the price per kWh, and how does it escalate? Compare against a realistic forecast of your grid tariff, not today's price.
  2. What availability is committed? And what happens if the plant under-delivers?
  3. Who is responsible for fuel? Supply, quality, storage and price risk should be clearly allocated.
  4. What happens to heat? Is it included, priced separately, or wasted?
  5. How does the plant interact with the grid? Parallel operation, backup, islanding and export.
  6. Who operates and maintains it? Local staff, remote monitoring, spare parts.
  7. What happens at the end of the term? Extension, transfer of ownership or removal.

The commercial structures

Energy-as-a-Service Customer-owned Joint development
Capital from you None Full Shared
Who owns the plant Supplier You Joint venture
Who operates Supplier Supplier or you Agreed per project
What you pay for Energy delivered The plant, plus O&M Your share

Most industrial customers choose Energy-as-a-Service, because it keeps capital in the core business and puts performance risk with the party that runs the plant. We compare the models in detail in Energy-as-a-Service vs owning the plant.

How CNP delivers it

CNP develops, finances, builds, owns and operates onsite energy plants that run on local biomass and supply continuous power and heat. Plants are integrated behind the meter, in parallel with the grid or as an off-grid microgrid.

Next step

Assess your site. Share your load profile, heat demand and fuel availability and we will tell you whether behind-the-meter generation makes sense.

See if onsite energy works for your site.